Implementation of total quality management (TQM) in malaysian industrialized building system (IBS) projects

Authors

  • Aawag Mohsen Alawag Department of Civil and Environmental Engineering, University Technology of PETRONAS, Bandar Seri Iskandar, Tronoh (Malaysia)
  • Wesam Salah Alaloul Department of Civil and Environmental Engineering, University Technology of PETRONAS, Bandar Seri Iskandar, Tronoh (Malaysia)
  • M.S. Liew Department of Civil and Environmental Engineering, University Technology of PETRONAS, Bandar Seri Iskandar, Tronoh (Malaysia)
  • Muhammad Ali Musarat Department of Civil and Environmental Engineering, University Technology of PETRONAS, Bandar Seri Iskandar, Tronoh (Malaysia)
  • Abdullah O. Baarimah Department of Civil and Environmental Engineering, Universiti Teknologi PETRONAS, Bandar Seri Iskandar, Tronoh (Malaysia)

DOI:

https://doi.org/10.7764/RDLC.22.1.74

Keywords:

Malaysia, TQM Implementation, IBS, malaysian construction industry, awareness.

Abstract

Total Quality Management could be defined as a transformation in management style aimed at constantly increasing customer satisfaction via the design and improvement of organizational systems and processes. It is critical to use an industrialized building system to increase project successful implementation. Awareness of TQM advantages and its application could greatly improve project efficiency and performance. A literature search on TQM was done to determine the TQM implementation present state and level of awareness in IBS construction projects. The purpose of this study is to identify the current TQM implementation status in IBS projects and determine its level of awareness and potential benefits from the Malaysian construction stakeholders’ perception. A mixed approach was applied in this research with the participation of consultants, contractors, clients, and academicians from various construction industry public and private sectors in Malaysia. The questionnaire survey was used to conduct the study. A total of 371 questionnaires were collected, for a sample size of 265. The findings indicated that most construction organizations are unaware of the TQM approach. The Cronbach's Alpha coefficient achieved from the study was (0.934), indicating that the questionnaire was reliable. The statistical analysis revealed that increased efficiency, improved customer satisfaction, enhanced teamwork, increased profitability, and improved safety are the most essential TQM benefits that concerned the participants. Furthermore, the results of this study provide IBS construction practitioners with significant awareness of the components that empower TQM implementation in the construction sector. This study contributes to the understanding of TQM and project performance by demonstrating their capacity to enhance the Malaysian construction sector. Additionally, it was found that the Malaysian construction industry has not achieved a high level of quality implementation programs.

References

Abdullah, Mat Naim, Mohd Saidin Misnan, and Syamsul Hendra Mahmud. 2008. “Development of Quality Culture in Construction Firms : The Role of Leadership and Human Resource Management.” Pp. 888–905 in.

Abedi, Mohammad, Mohamad Syazli Fathi, and Norshakila Muhamad Rawai. 2012. “A Review of Industrialised Building System in Malaysian Con-struction Industry.” P. 5 in Management in Construction Research Association (MiCRA) Postgraduate Conference.

Ahmad, Md Fauzi, Phoi Soo Nee, Nik Hisyamudin Muhd Nor, Chan Shiau Wei, Mohd Fahrul Hassan, and Nor Aziati Abdul Hamid. 2017. “Total Quality Management Practices in Malaysia Healthcare Industry.” in AIP Conference Proceedings. Vol. 1891.

Akadiri, Oluwole P. 2011. “Development of a Multi-Criteria Approach for the Selection of Sustainable Materials for Building Projects.”

Al-Aidrous, Al Hussein M. H., Y. Rahmawati, K. Wan Yusof, A. Omar Baarimah, and A. M. Alawag. 2021. “Review of Industrialized Buildings Experi-ence in Malaysia: An Example of a Developing Country.” IOP Conference Series: Earth and Environmental Science 682(1).

Al-Shdaifat, Emad A. 2015. “Implementation of Total Quality Management in Hospitals.” Journal of Taibah University Medical Sciences 10(4):461–66.

Alaloul, Wesam Salah, Mohd Shahir Liew, and Noor Amila Wan Abdullah Zawawi. 2015. “The Characteristics of Coordination Process in Construction Projects.” Pp. 159–64 in 2nd International Symposium on Technology Management and Emerging Technologies, ISTMET 2015 - Proceeding. IEEE.

Alaloul, Wesam Salah, Mohd Shahir Liew, and Noor Amila B. W. A. Zawawi. 2016. “A Framework for Coordination Process into Construction Projects.” P. 79 in MATEC Web of Conferences. Vol. 66. EDP Sciences.

Alawag, Aawag Mohsen, Wesam Salah Alaloul, M. S. Liew, Mohammed Ali Mohammed Al-bared, Noor Amila, Wan Abdullah, and Syed Ammad. 2021. The Implementation of the Industrialized Building System in the Malaysian Construction Industry — a Comprehensive Review. Springer Singapore.

Alawag, Aawag Mohsen, Wesam Salah Alaloul, M. S. Liew, Muhammad Ali Musarat, Abdullah O. Baarimah, Syed Saad, and Syed Ammad. 2022. “Critical Success Factors Influencing Total Quality Management In Industrialised Building System : A Case Of Malaysian Construction Industry.” Ain Shams Engineering Journal (xxxx):101877.

Alawag, Aawag Mohsen, Wesam Salah Alaloul, M. S. Liew, Al Hussein M. H. Al-Aidrous, Syed Saad, and Syed Ammad. 2020. “Total Quality Manage-ment Practices and Adoption in Construction Industry Organizations: A Review.” in 2020 2nd International Sustainability and Resilience Confer-ence: Technology and Innovation in Building Designs.

Alofi, Khalid, and Ahmed Younes. 2019. “Total Quality Management (TQM) Implementation in the Manufacturing Sector in Saudi Arabia: A Systematic Review.” Business and Management Research 8(1):41.

Altaf, Muhammad, Wesam Salah Alaloul, Sheharyar Khan, M. S. Liew, Muhammad Ali Musarat, and Alawag Aawag Mohsen. 2021. “Value Analysis in Construction Projects with BIM Implementation: A Systematic Review.” Pp. 51–56 in 2021 International Conference on Decision Aid Sciences and Application (DASA). IEEE.

Altahayneh, Ziad Lutfi. 2014. “Implementation of Total Quality Management in Colleges of Physical Education in Jordan.” International Journal of Business and Social Science 5(5):109–17.

Alzubi, Khalid Mhmoud, Wesam Salah Alaloul, Marsail Al Salaheen, Abdul Hannan Qureshi, Muhammad Ali Musarat, and Aawag Mohsen Alawag. 2022. “Reviewing the Applications of Internet of Things in Construction Projects.” Pp. 169–73 in 2022 International Conference on Decision Aid Sciences and Applications (DASA). IEEE.

Ammad, Syed, Wesam Salah Alaloul, Syed Saad, Muhammad Altaf, Aawag Mohsen Alawag, and Mujahid Ali. 2021. “Building Information Modelling (BIM) and Occupational Safety in Infrastructure Projects.” Pp. 240–44 in 2021 International Conference on Data Analytics for Business and Indus-try (ICDABI). IEEE.

Anuar, J., N. Sumarjan, and S. M. Radzi. 2017. “Total Quality Management (TQM) Practices: Challenges Faced by the Hotel Managers.” Journal of Tourism, Hospitality & Culinary Arts (JTHCA) 2017 293(2):293–304.

Baarimah, Abdullah O, Wesam Salah Alaloul, M. S. Liew, Al-Hussein M. H. Al-Aidrous, Aawag Mohsen Alawag, and Muhammad Ali Musarat. 2021. “Integration of Building Information Modeling (BIM) and Value Engineering in Construction Projects: A Bibliometric Analysis.” Pp. 362–67 in 2021 Third International Sustainability and Resilience Conference: Climate Change. IEEE.

Baarimah, Abdullah O., Wesam Salah Alaloul, M. S. Liew, Aawag Mohsen Alawag, Muhammad Ali Musarat, and Khalid Mhmoud Alzubi. 2021. “Cur-rent State of Post-Disaster Reconstruction Projects: A Bibliometric Analysis.” 2021 International Conference on Decision Aid Sciences and Applica-tion, DASA 2021 108–13.

Baharuddin, Mohd Nurfaisal, Nur Fadhilah Bahardin, Mohd Azian Zaidi, and Ikhwan Lokman. 2016. “A Barriers and Challenging Criteria of IBS Form-work : A Current Scenario Amongs Stakeholder.” 39(2015):14–21.

Bolatan, Gulin Idil Sonmezturk, Sitki Gozlu, Lutfihak Alpkan, and Selim Zaim. 2016. “The Impact of Technology Transfer Performance on Total Quality Management and Quality Performance.” Procedia - Social and Behavioral Sciences 235(October):746–55.

Chai, Teck Jung, Cher Siang Tan, Tio Kiong Chow, Philip Chie Hui Ling, and Heng Boon Koh. 2019. “A Review on Prefab Industrialised Building System Modular Construction in Malaysia: The Perspective of Non-Structural Studies.” Lecture Notes in Civil Engineering 19:11–21.

Chan, Albert P. C., David Scott, and Edmond W. M. Lam. 2002. “Framework of Success Criteria for Design/Build Projects.” Journal of Management in Engineering 18(3):120–28.

CIDB. 2012. “Management Factors for Successful IBS Projects Implementation.” Pp. 99–107 in Vol. 4.

CIDB ibs. n.d. “IBS-Net Management Information System Manufacturers IBS-Net Management Information System Manufacturers.”

Drost, A. Ellen. 2011. “Validity and Reliability in Social Science Research.” Education Research and Perspectives 38(1):105–23.

Engineering, M. T. D. Acpi, Jalan Batu, Precast Column, Precast Beam, and Negeri Sembilan. 2013. “IBS-Net Management Information System Manu-facturers IBS-Net Management Information System Manufacturers.” 1–31.

Fathi, Syazli, Abdul Karim Mirasa, and Muhammad Abedi. 2012. “Construction Industry Experience of IBS in Malaysia.” in In 9th International Con-gress on Civil Engineering (9ICCE).

Flynn, Barbara B., Roger G. Schroeder, and Sadao Sakakibara. 1994. “A Framework for Quality Management Research and an Associated Measurement Instrument.” Journal of Operations Management 11(4):339–66.

Gudiene, Neringa, Audrius Banaitis, and Nerija Banaitiene. 2013. “Evaluation of Critical Success Factors for Construction Projects - an Empirical Study in Lithuania.” International Journal of Strategic Property Management 17(1):21–31.

Hussain, M. R. 2015. “Malaysia Productivity Corporation (MPC).” 22nd Productivity Report 2014/2015 144.

HYVÄRI, IRJA. 2006. “S Uccess of P Rojects in D Ifferent.” Project Management Journal 37(4):31–42.

Idris, Fazli. 2011. “Total Quality Management (TQM) and Sustainable Company Performances: Examining the Relationship in Malaysian Firms.” Inter-national Journal of Business & Society 12(1).

Kahreh, Zahra Safari, Alireza Shirmohammadi, and Mohammad Safari Kahreh. 2014. “Explanatory Study Towards Analysis the Relationship between Total Quality Management and Knowledge Management.” Procedia - Social and Behavioral Sciences 109:600–604.

Kamar, Kamarul Anuar Mohamad, and Zuhairi Abd Hamid. 2011. “Supply Chain Strategy for Contractor in Adopting Industrialised Building System (IBS).” Australian Journal of Basic and Applied Sciences 5(12):2552–57.

Koota, Jaana. 2003. “Market Review and Study of Success Characteristics in Construction Companies. Case: United States.” VTT Tiedotteita - Valtion Teknillinen Tutkimuskeskus (2195):3–41.

Mahamid, Ibrahim. 2020. “Study of Relationship between Rework and Labor Productivity In Building Construction Projects.” Revista de La Construc-cion 19(1):30–40.

Management, Estate. 2021. “TOTAL QUALITY MANAGEMENT: CASE STUDY OF CONSTRUCTION COMPANIES IN KOSOVO Abetare Prebreza University of Pristina ‘Hasan Prishtina’, Kosovo.” 9(1):54–73.

Maqsoom, Ahsen, Sajjad Bajwa, Hafiz Zahoor, Muhammad Jamaluddin Thaheem, and Muhammad Dawood. 2019. “Optimizing Contractor’s Selection and Bid Evaluation Process in Construction Industry: Client’s Perspective.” Revista de La Construccion 18(3):445–58.

Mohd Fateh, Mohd Ashraf, and Mohammad Fadhil Mohammad. 2021. “The Framework of Factors for the Improvement of the Significant Clauses in the Standard Form of Contract for the IBS Construction Approach in Malaysia.” International Journal of Sustainable Construction Engineering and Technology 12(1).

Mohsen, A., R. Yunus, R. Handan, N. Kasim, and K. Hussain. 2019. “Determining Factors for Enhanced Skilled Worker Requirements in IBS Construction Projects in Malaysia.” in IOP Conference Series: Earth and Environmental Science. Vol. 220.

Mohsen, Aawag, Wesam Salah Alaloul, M. S. Liew, Muhammad Ali Musarat, Abdullah O. Baarimah, Khalid Mhmoud Alzubi, and Muhammad Altaf. 2021. “Impact of the COVID-19 Pandemic on Construction Industry in Malaysia.” Pp. 237–41 in 2021 Third International Sustainability and Resil-ience Conference: Climate Change. IEEE.

Musarat, Muhammad Ali, Wesam Salah Alaloul, and M. S. Liew. 2021. “Construction Machinery Hire Rates Deviation in Malaysia: An Inflation Rate Effect Analysis.” Revista de La Construccion 20(1):91–105.

Musarat, Muhammad Ali, Nasir Hameed, Muhammad Altaf, Wesam Salah Alaloul, Marsail Al Salaheen, and Aawag Mohsen Alawag. 2021. “Digital Transformation of the Construction Industry: A Review.” 2021 International Conference on Decision Aid Sciences and Application, DASA 2021 897–902.

Nasir, Najuwa Mohd, Mohd Nasrun Mohd Nawi, Mohd Kamarul Irwan Abdul Rahim, Ahmad Yusni Bahaudin, and Afirudin Tapa. 2016. “A Review of Delay Factors in Malaysian Industrialized Building System (IBS) Construction Project.” ARPN Journal of Engineering and Applied Sciences 11(16):9868–73.

Nasrun, Mohd, Mohd Nawi, and Zuhairi Abd Hamid. 2012. “Critical Success Factors for Improving Team Integration in Industrialised Building System ( IBS ) Construction Projects :THE MALAYSIAN CASE.” Malaysian Construction Research Journal 10(April 2016):44–62.

Nawi, Mnm, Hs Anuar, and Angela Lee. 2013. “A Review of IBS Malaysian Current and Future Study.” International Journal of … 2(10):2378–83.

Othman, Idris, Siti Norfarahhanim Mohd Ghani, and Shim Woon Choon. 2019. “The Total Quality Management (TQM) Journey of Malaysian Building Contractors.” Ain Shams Engineering Journal (xxxx).

Othuman Mydin, M. A., N. Md Sani, M. Taib, and N. Mohd Alias. 2014. “Imperative Causes of Delays in Construction Projects from Developers’ Out-look.” in MATEC Web of Conferences. Vol. 10.

Peter, J. Paul. 1979. “Reliability: A Review of Psychometric Basics and Recent Marketing Practices.” Journal of Marketing Research 16(1):6.

Pheng, Low Sui, and Quek Tai Chuan. 2006. “PROJECT Environmental Factors and Work Performance of Project Managers in the Construction Indus-try.” International Journal of Project Management 24 24:24–37.

Pozin, Mohd Affendi Ahmad, and Mohd Nasrun Mohd Nawi. 2017. “The Communication in Industrialised Building System (IBS) Construction Project: Virtual Environment.” in AIP Conference Proceedings. Vol. 1891.

Preece, C., Pheng, L., Padfield, R., & Papargyropoulou, E. 2011. “Management and Innovation for a Sustainable Built Environment 20 – 23 June 2011, Amsterdam, The Netherlands ISBN: 9789052693958.” Occupational Health (June).

Rahim, Asiah Abdul, and Sara Latif Qureshi. 2018. “A Review of IBS Implementation in Malaysia and Singapore.” Journal of the Malaysian Institute of Planners 16(2):323–33.

Richard, Jimoh, Oyewobi Luqman, Waziri Mohammed, and Isa Rasheed. 2017. “Total Quality Management Practices in the Nigerian Construction Industry.” 7(2):65–76.

Rozaimi A Samad, Ismar Minang Satotoy Usman, and Sudarshan N Raman. 2020. “A Review on Construction of Additional Building School Using Industrialized Building System (IBS) in Sarawak, Malaysia.” Journal of Xi’an University of Architecture & Technology Volume XII(Issue XI):706–16.

Samsudin, Noor Sahidah, Seti Mariam Ayop, Siti Suhaidah Sahab, and Zulhabri Ismail. 2012. “Problems and Issues on the Implementation of Quality Management System in Construction Projects.” Pp. 684–89 in ISBEIA 2012 - IEEE Symposium on Business, Engineering and Industrial Applica-tions. IEEE.

Sanders, Patricia. 1982. “A New Way of Viewing Phenomenology.” Academy of Management Review 7(3):353–60.

Shah, Syyed Adnan Raheel, Ahsan Nawaz, Muhammad Abid, Ahmed Salman Malik, Saleem Fakhar, and Mudassir Elahi. 2021. “Identification of Risk Factors Involved in SCP of Developing Coun-Tries-Establishing Guidelines: An Analysis of Mixed Method Se-Quential Approach.” Revista de La Construccion 20(3):407–26.

Silva, F. A. N., M. T. A. Silva, J. M. P. Q. Delgado, A. C. Azevedo, and G. F. C. Pereira. 2022. “Construction and Demolition Waste as Raw Material in Pavements Layers.” Revista de La Construccion 21(1):184–92.

Tayeh, Bassam A., Khalid Al Hallaq, Wesam Salah Alaloul, and Ahmed Reyad Kuhail. 2018. “Factors Affecting the Success of Construction Projects in Gaza Strip.” The Open Civil Engineering Journal 12(1):301–15.

Tey, Lian Seng, and Teck Loon Ooi. 2014. “Exploring the Barriers and the Level of TQM Implementation in Malaysian Construction Industry.” Research Journal of Applied Sciences, Engineering and Technology 7(16):3419–24.

Toke, Lalit K., and Shyamkumar D. Kalpande. 2020. “Total Quality Management in Small and Medium Enterprises: An Overview in Indian Context.” Quality Management Journal 27(3):159–75.

Turk, Murat A. 2006. “ISO 9000 in Construction: An Examination of Its Application in Turkey.” Building and Environment 41(4):501–11.

Venables, Tim, James Barlow, and David Gann. 2004. The Housing Forum Manufacturing Excellence.

Ynoh, Muhammad Naqib Mat, and Khairul Anuar Mohd Ali. 2015. “Total Quality Management Approach for Malaysian Food Industry: Conceptual Framework.” International Journal of Business and Social Science 6(1):405–9.

Yusr, Maha Mohammed, Sany Sanuri Mohd Mokhtar, Abdul Rahim Othman, and Yaty Sulaiman. 2017. “Does Interaction between TQM Practices and Knowledge Management Processes Enhance the Innovation Performance?” International Journal of Quality and Reliability Management 34(7):955–74.

Zaini, Nadia, and Ibrahim Siti Halipah. 2015. “A Review on Embodied Energy Through Industrialised Building System Implementation in Construction Industries.” Sains Humanika 6(1):43–48.

Downloads

Published

2023-04-30 — Updated on 2023-05-03

Versions

How to Cite

Alawag, A. M. ., Alaloul, W. S., Liew, M. ., Ali Musarat, M. ., & O. Baarimah, A. (2023). Implementation of total quality management (TQM) in malaysian industrialized building system (IBS) projects. Revista De La Construcción. Journal of Construction, 22(1), 74–86. https://doi.org/10.7764/RDLC.22.1.74 (Original work published April 30, 2023)